Tex. Prop. Code Section 53.161
Bond Requirements After Order to Remove


(a)

In the order removing a lien, the court shall set the amount of security that the claimant may provide in order to stay the removal of the claim or lien. The sum must be an amount that the court determines is a reasonable estimate of the costs and attorney’s fees the movant is likely to incur in the proceeding to determine the validity or enforceability of the lien. The sum may not exceed the amount of the lien claim.

(b)

The court shall stay the order removing the lien if the claimant files a bond or a deposit in lieu of a bond in the amount set in the order with the clerk of the court not later than the 30th day after the date the order is entered by the court unless, for good cause, the court orders a later date for filing the bond or the deposit in lieu of a bond. If the court fails to set the amount of the security required, the amount required is the amount of the lien claim.

(c)

The bond must be:

(1)

executed by a corporate surety authorized to do business in this state and licensed by this state to execute bonds as surety; and

(2)

conditioned on the claimant’s payment of any final judgment rendered against the claimant in the proceeding for attorney’s fees and costs to the movant under Section 53.156 (Costs and Attorney’s Fees).

(d)

In lieu of filing a bond, the claimant may deposit in the amount set by the court for the surety bond:

(1)

cash;

(2)

a negotiable obligation of the federal government or a federal agency; or

(3)

a negotiable obligation of a financial institution chartered by the federal or state government that is insured by the federal government or a federal agency.

(e)

A deposit made under Subsection (d) must be conditioned in the same manner as a surety bond. Any interest accrued on the deposit amount is a part of the deposit.

(f)

If the claimant fails to file the bond or the deposit in lieu of the bond in compliance with this section, the owner may file:

(1)

a certified copy of the order; and

(2)

a certificate from the clerk of the court stating that:

(A)

no bond or deposit in lieu of the bond was filed within 30 days after the date the order was entered by the court; and

(B)

no order staying the order to remove the lien was entered by the court.

(g)

The claim or lien is removed and extinguished as to a creditor or subsequent purchaser for valuable consideration who obtains an interest in the property after the certified copy of the order and certificate of the clerk of the court are filed with the county clerk. The removal of the lien does not constitute a release of the liability of the owner, if any, to the claimant.
Added by Acts 1997, 75th Leg., ch. 526, Sec. 17, eff. Sept. 1, 1997.

Source: Section 53.161 — Bond Requirements After Order to Remove, https://statutes.­capitol.­texas.­gov/Docs/PR/htm/PR.­53.­htm#53.­161 (accessed Apr. 20, 2024).

53.001
Definitions
53.002
More than One Original Contractor
53.003
Notices
53.021
Persons Entitled to Lien
53.022
Property to Which Lien Extends
53.023
Payment Secured by Lien
53.024
Limitation on Subcontractor’s Lien
53.025
Limitation on Ordinary Retainage Lien
53.026
Sham Contract
53.051
Necessary Procedures
53.052
Filing of Affidavit
53.054
Contents of Affidavit
53.055
Notice of Filed Affidavit
53.056
Derivative Claimant: Notice to Owner and Original Contractor
53.057
Derivative Claimant: Notice of Claim for Unpaid Retainage
53.081
Authority to Withhold Funds for Benefit of Claimants
53.082
Time for Which Funds Are Withheld
53.084
Owner’s Liability
53.085
Affidavit Required
53.101
Funds Required to Be Reserved
53.102
Payment Secured by Reserved Funds
53.103
Lien on Reserved Funds
53.104
Preferences
53.105
Owner’s Liability for Failure to Reserve Funds
53.106
Affidavit of Completion
53.107
Notice Relating to Termination of Work or Abandonment of Performance by Original Contractor or Owner
53.121
Preference over Other Creditors
53.122
Equality of Mechanic’s Liens
53.123
Priority of Mechanic’s Lien over Other Liens
53.124
Inception of Mechanic’s Lien
53.151
Enforcement of Remedies Against Money Due Original Contractor or Subcontractor
53.152
Release of Claim or Lien
53.153
Defense of Actions
53.154
Foreclosure
53.155
Transfer of Property Sold
53.156
Costs and Attorney’s Fees
53.157
Discharge of Lien
53.158
Period for Bringing Suit to Foreclose Lien
53.159
Obligation to Furnish Information
53.160
Summary Motion to Remove Invalid or Unenforceable Lien
53.161
Bond Requirements After Order to Remove
53.162
Revival of Removed Lien
53.171
Bond
53.172
Bond Requirements
53.173
Notice of Bond
53.174
Recording of Bond and Notice
53.175
Action on Bond
53.201
Bond
53.202
Bond Requirements
53.203
Recording of Bond and Contract
53.204
Reliance on Record
53.205
Enforceable Claims
53.206
Perfection of Claim
53.207
Owner’s Notice of Claim to Surety
53.208
Action on Bond
53.210
Claims in Excess of Bond Amount
53.211
Attempted Compliance
53.231
Lien
53.232
To Whom Notice Given
53.233
Contents of Notice
53.234
Time for Notice
53.235
Official to Retain Funds
53.236
Bond for Release of Lien
53.237
Bond Requirements
53.238
Notice of Bond
53.239
Action on Bond
53.251
Procedures for Residential Construction Projects
53.254
Contractual Requirements for Lien on Homestead
53.255
Disclosure Statement Required for Residential Construction Contract
53.256
List of Subcontractors and Suppliers
53.257
Provisions Related to Closing of Loan for Construction of Improvements
53.258
Disbursements of Funds
53.259
Final Bills-paid Affidavit Required
53.260
Conveyance to Contractor Not Required
53.281
Waiver and Release of Lien or Payment Bond Claim
53.282
Conditions for Waiver, Release, or Impairment of Lien or Payment Bond Claim
53.283
Unconditional Waiver and Release: Payment Required
53.284
Forms for Waiver and Release of Lien or Payment Bond Claim
53.286
Public Policy
53.287
Certain Agreements Exempt

Accessed:
Apr. 20, 2024

§ 53.161’s source at texas​.gov