Tex. Prop. Code Section 53.160
Summary Motion to Remove Invalid or Unenforceable Lien


(a)

In a suit brought to foreclose a lien or to declare a claim or lien invalid or unenforceable, a party objecting to the validity or enforceability of the claim or lien may file a motion to remove the claim or lien. The motion must be verified and state the legal and factual basis for objecting to the validity or enforceability of the claim or lien. The motion may be accompanied by supporting affidavits.

(b)

The grounds for objecting to the validity or enforceability of the claim or lien for purposes of the motion are limited to the following:

(1)

notice of claim was not timely furnished to the owner or original contractor as required by Section 53.056 (Derivative Claimant: Notice to Owner and Original Contractor) or 53.057 (Derivative Claimant: Notice of Claim for Unpaid Retainage);

(2)

an affidavit claiming a lien failed to comply with Section 53.054 (Contents of Affidavit) or was not filed as required by Section 53.052 (Filing of Affidavit);

(3)

notice of the filed affidavit was not furnished to the owner or original contractor as required by Section 53.055 (Notice of Filed Affidavit);

(4)

the deadlines for perfecting a lien claim for retainage under this chapter have expired and the owner complied with the requirements of Section 53.101 (Funds Required to Be Reserved) and paid the retainage and all other funds owed to the original contractor before:

(A)

the claimant perfected the lien claim; and

(B)

the owner received a notice of the claim as required by this chapter;

(5)

all funds subject to the notice of a claim to the owner and a notice regarding the retainage have been deposited in the registry of the court and the owner has no additional liability to the claimant;

(6)

when the lien affidavit was filed on homestead property:

(A)

no contract was executed or filed as required by Section 53.254 (Contractual Requirements for Lien on Homestead);

(B)

the affidavit claiming a lien failed to contain the notice as required by Section 53.254 (Contractual Requirements for Lien on Homestead); or

(C)

the notice of the claim failed to include the statement required by Section 53.254 (Contractual Requirements for Lien on Homestead); and

(7)

the claimant executed a valid and enforceable waiver or release of the claim or lien claimed in the affidavit.

(c)

The claimant is not required to file a response. The claimant and any other party that has appeared in the proceeding must be notified by at least 30 days before the date of the hearing on the motion. A motion may not be heard before the 30th day after the date the claimant answers or appears in the proceeding. The claimant must be allowed expedited discovery regarding information relevant to the issues listed under Subsection (b).

(d)

At the hearing on the motion, the burden is on:

(1)

the claimant to prove that the notice of claim and affidavit of lien were furnished to the owner and original contractor as required by this chapter; and

(2)

the movant to establish that the lien should be removed for any other ground authorized by this section.

(e)

The court shall promptly determine a motion to remove a claim or lien under this section. If the court determines that the movant is not entitled to remove the lien, the court shall enter an order denying the motion. If the court determines that the movant is entitled to remove the lien, the court shall enter an order removing the lien claimed in the lien affidavit. A party to the proceeding may not file an interlocutory appeal from the court’s order.

(f)

Any admissible evidence offered at the hearing may be admitted in the trial of the case. The court’s order under Subsection (e) is not admissible as evidence in determining the validity and enforceability of the claim or lien.
Added by Acts 1997, 75th Leg., ch. 526, Sec. 17, eff. Sept. 1, 1997.
Amended by:
Acts 2011, 82nd Leg., R.S., Ch. 499 (H.B. 1390), Sec. 8, eff. September 1, 2011.
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 24, eff. January 1, 2022.

Source: Section 53.160 — Summary Motion to Remove Invalid or Unenforceable Lien, https://statutes.­capitol.­texas.­gov/Docs/PR/htm/PR.­53.­htm#53.­160 (accessed Jun. 5, 2024).

53.001
Definitions
53.002
More than One Original Contractor
53.003
Notices
53.021
Persons Entitled to Lien
53.022
Property to Which Lien Extends
53.023
Payment Secured by Lien
53.024
Limitation on Subcontractor’s Lien
53.025
Limitation on Ordinary Retainage Lien
53.026
Sham Contract
53.051
Necessary Procedures
53.052
Filing of Affidavit
53.054
Contents of Affidavit
53.055
Notice of Filed Affidavit
53.056
Derivative Claimant: Notice to Owner and Original Contractor
53.057
Derivative Claimant: Notice of Claim for Unpaid Retainage
53.081
Authority to Withhold Funds for Benefit of Claimants
53.082
Time for Which Funds Are Withheld
53.084
Owner’s Liability
53.085
Affidavit Required
53.101
Funds Required to Be Reserved
53.102
Payment Secured by Reserved Funds
53.103
Lien on Reserved Funds
53.104
Preferences
53.105
Owner’s Liability for Failure to Reserve Funds
53.106
Affidavit of Completion
53.107
Notice Relating to Termination of Work or Abandonment of Performance by Original Contractor or Owner
53.121
Preference over Other Creditors
53.122
Equality of Mechanic’s Liens
53.123
Priority of Mechanic’s Lien over Other Liens
53.124
Inception of Mechanic’s Lien
53.151
Enforcement of Remedies Against Money Due Original Contractor or Subcontractor
53.152
Release of Claim or Lien
53.153
Defense of Actions
53.154
Foreclosure
53.155
Transfer of Property Sold
53.156
Costs and Attorney’s Fees
53.157
Discharge of Lien
53.158
Period for Bringing Suit to Foreclose Lien
53.159
Obligation to Furnish Information
53.160
Summary Motion to Remove Invalid or Unenforceable Lien
53.161
Bond Requirements After Order to Remove
53.162
Revival of Removed Lien
53.171
Bond
53.172
Bond Requirements
53.173
Notice of Bond
53.174
Recording of Bond and Notice
53.175
Action on Bond
53.201
Bond
53.202
Bond Requirements
53.203
Recording of Bond and Contract
53.204
Reliance on Record
53.205
Enforceable Claims
53.206
Perfection of Claim
53.207
Owner’s Notice of Claim to Surety
53.208
Action on Bond
53.210
Claims in Excess of Bond Amount
53.211
Attempted Compliance
53.231
Lien
53.232
To Whom Notice Given
53.233
Contents of Notice
53.234
Time for Notice
53.235
Official to Retain Funds
53.236
Bond for Release of Lien
53.237
Bond Requirements
53.238
Notice of Bond
53.239
Action on Bond
53.251
Procedures for Residential Construction Projects
53.254
Contractual Requirements for Lien on Homestead
53.255
Disclosure Statement Required for Residential Construction Contract
53.256
List of Subcontractors and Suppliers
53.257
Provisions Related to Closing of Loan for Construction of Improvements
53.258
Disbursements of Funds
53.259
Final Bills-paid Affidavit Required
53.260
Conveyance to Contractor Not Required
53.281
Waiver and Release of Lien or Payment Bond Claim
53.282
Conditions for Waiver, Release, or Impairment of Lien or Payment Bond Claim
53.283
Unconditional Waiver and Release: Payment Required
53.284
Forms for Waiver and Release of Lien or Payment Bond Claim
53.286
Public Policy
53.287
Certain Agreements Exempt

Accessed:
Jun. 5, 2024

§ 53.160’s source at texas​.gov