Tex.
Educ. Code Section 51.782
Contracts for Facilities: Construction Manager-at-risk
(a)
An institution may use the construction manager-at-risk method for the construction, rehabilitation, alteration, or repair of a facility. In using that method and in entering into a contract for the services of a construction manager-at-risk, a board shall follow the procedures prescribed by this section.(b)
A construction manager-at-risk is a sole proprietorship, partnership, corporation, or other legal entity that assumes the risk for construction, rehabilitation, alteration, or repair of a facility at the contracted price as a general contractor and provides consultation to the institution regarding construction during and after the design of the facility.(c)
Before or concurrently with selecting a construction manager-at-risk, the board shall select or designate an engineer or architect who shall prepare the construction documents for the project and who has full responsibility for complying with Chapter 1001 (Texas Board of Professional Engineers and Land Surveyors) or 1051 (Texas Board of Architectural Examiners; General Provisions Affecting Architects, Landscape Architects, and Interior Designers; Provisions Affecting Only Architects), Occupations Code, as applicable. If the engineer or architect is not a full-time employee of the institution, the board shall select the engineer or architect on the basis of demonstrated competence and qualifications as provided by Section 2254.004 (Contract for Professional Services of Architect, Engineer, or Surveyor), Government Code. The institution’s engineer, architect, or construction manager-agent for a project may not serve, alone or in combination with another, as the construction manager-at-risk unless the engineer or architect is hired to serve as the construction manager-at-risk under a separate or concurrent procurement conducted in accordance with this subchapter. This subsection does not prohibit the institution’s engineer or architect from providing customary construction phase services under the engineer’s or architect’s original professional service agreement in accordance with applicable licensing laws.(d)
The board shall provide or contract for, independently of the construction manager-at-risk, the inspection services, the testing of construction materials engineering, and the verification testing services necessary for acceptance of the facility by the institution. The board shall select those services for which it contracts in accordance with Section 2254.004 (Contract for Professional Services of Architect, Engineer, or Surveyor), Government Code.(e)
The board shall select the construction manager-at-risk in either a one-step or two-step process. The board shall prepare a request for proposals, in the case of a one-step process, or a request for qualifications, in the case of a two-step process, that includes general information on the project site, project scope, schedule, selection criteria, estimated budget, and the time and place for receipt of proposals or qualifications, as applicable, a statement as to whether the selection process is a one-step or two-step process, and other information that may assist the board in its selection of a construction manager-at-risk. The board shall state the selection criteria in the request for proposals or qualifications, as applicable. The selection criteria may include the offeror’s experience, past performance, safety record, proposed personnel and methodology, and other appropriate factors that demonstrate the capability of the construction manager-at-risk. If a one-step process is used, the board may request, as part of the offeror’s proposal, proposed fees and prices for fulfilling the general conditions. If a two-step process is used, the board may not request fees or prices in step one. In step two, the board may request that five or fewer offerors, selected solely on the basis of qualifications, provide additional information, including the construction manager-at-risk’s proposed fee and its price for fulfilling the general conditions.(f)
The board shall publish the request for qualifications in a manner prescribed by the board.(g)
At each step, the board shall receive, publicly open, and read aloud the names of the offerors. At the appropriate step, the board shall also read aloud the fees and prices, if any, stated in each proposal as the proposal is opened. Within 45 days after the date of opening the proposals, the board or its representative shall evaluate and rank each proposal submitted in relation to the criteria set forth in the request for proposals.(h)
The board or its representative shall select the offeror that submits the proposal that offers the best value for the institution based on the published selection criteria and on its ranking evaluation. The board or its representative shall first attempt to negotiate with the selected offeror a contract. If the board or its representative is unable to negotiate a satisfactory contract with the selected offeror, the board or its representative shall, formally and in writing, end negotiations with that offeror and proceed to negotiate with the next offeror in the order of the selection ranking until a contract is reached or negotiations with all ranked offerors end.(i)
A construction manager-at-risk shall publicly advertise, in the manner prescribed by the institution, and receive bids or proposals from trade contractors or subcontractors for the performance of all major elements of the work other than general conditions work. A construction manager-at-risk may seek to perform major elements of the work itself if the construction manager-at-risk submits its bid or proposal for that work in the same manner as all other trade contractors or subcontractors and if the board determines that the construction manager-at-risk’s bid or proposal provides the best value for the institution. If no satisfactory bid or proposal for a major element of the work is received in the time allowed, the board may negotiate directly with the construction manager-at-risk for performance of that work. The board may negotiate directly with the manager-at-risk for the performance of minor elements of the work that are not included in major work packages.(j)
The construction manager-at-risk and the board or its representative shall review all trade contractor or subcontractor bids or proposals in a manner that does not disclose the contents of the bid or proposal during the selection process to a person not employed by the construction manager-at-risk, engineer, architect, or institution. All bids or proposals shall be made public after the award of the contract or within seven days after the date of final selection of bids and proposals, whichever is later.(k)
If the construction manager-at-risk reviews, evaluates, and recommends to the board a bid or proposal from a trade contractor or subcontractor but the board requires another bid or proposal to be accepted, the institution shall compensate the construction manager-at-risk by a change in price, time, or guaranteed maximum cost for any additional cost and risk that the construction manager-at-risk may incur because of the board’s requirement that another bid or proposal be accepted.(l)
If a selected trade contractor or subcontractor defaults in the performance of its work or fails to execute a subcontract after being selected in accordance with this section, the construction manager-at-risk may, without advertising, itself fulfill the contract requirements or select a replacement trade contractor or subcontractor to fulfill the contract requirements.(m)
If a fixed contract amount or guaranteed maximum price has not been determined at the time the contract is awarded, the penal sums of the performance and payment bonds delivered to the institution must each be in an amount equal to the project budget, as set forth in the request for qualifications. The construction manager shall deliver the bonds not later than the 10th day after the date the construction manager executes the contract unless the construction manager furnishes a bid bond or other financial security acceptable to the institution to ensure that the construction manager will furnish the required performance and payment bonds when a guaranteed maximum price is established.
Source:
Section 51.782 — Contracts for Facilities: Construction Manager-at-risk, https://statutes.capitol.texas.gov/Docs/ED/htm/ED.51.htm#51.782
(accessed Jun. 5, 2024).