Tex. Prop. Code Section 28.006
No Waiver


(a)

Except as provided by Subsection (b), an attempted waiver of a provision of this chapter is void.

(b)

A written contract between an owner and a contractor for improvements to or construction of a single-family residence may provide that the payment required under Section 28.002 (Prompt Pay Required)(a) be made not later than a date that occurs before the 61st day after the date the owner receives the payment request. Notwithstanding Section 28.004 (Interest on Overdue Payment)(b), an unpaid amount under contract subject to this subsection that allows payment later than the date otherwise required under Section 28.002 (Prompt Pay Required)(a) bears interest at the rate of 1-1/2 percent each month.
Added by Acts 1993, 73rd Leg., ch. 479, Sec. 1, eff. Sept. 1, 1993.

Source: Section 28.006 — No Waiver, https://statutes.­capitol.­texas.­gov/Docs/PR/htm/PR.­28.­htm#28.­006 (accessed Jun. 5, 2024).

Accessed:
Jun. 5, 2024

§ 28.006’s source at texas​.gov