Tex. Nat. Resources Code Section 133.050
Issuance of Certificate


(a)

If, after inspection, the commission determines that the barriers described in an approved application conform with the plan and comply with this subchapter, and the rules or orders adopted under this subchapter, the commission must issue a safety certificate to the person responsible for the pit.

(b)

If, after inspection, the commission determines that a barrier does not comply with this subchapter or a rule or order adopted under this subchapter, the commission shall give the applicant written notice of any defects in that barrier and shall allow the applicant a reasonable time, not to exceed 60 days from the day notice is received, to cure the defects.
Added by Acts 1991, 72nd Leg., ch. 668, Sec. 1, eff. Aug. 26, 1991.

Source: Section 133.050 — Issuance of Certificate, https://statutes.­capitol.­texas.­gov/Docs/NR/htm/NR.­133.­htm#133.­050 (accessed Jun. 5, 2024).