Tex. Local Gov't Code Section 212.009
Approval Procedure: Initial Approval


(a)

The municipal authority responsible for approving plats shall approve, approve with conditions, or disapprove a plat within 30 days after the date the plat is filed. A plat is approved by the municipal authority unless it is disapproved within that period and in accordance with Section 212.0091 (Approval Procedure: Conditional Approval or Disapproval Requirements).

(b)

If an ordinance requires that a plat be approved by the governing body of the municipality in addition to the planning commission, the governing body shall approve, approve with conditions, or disapprove the plat within 30 days after the date the plat is approved by the planning commission or is approved by the inaction of the commission. A plat is approved by the governing body unless it is disapproved within that period and in accordance with Section 212.0091 (Approval Procedure: Conditional Approval or Disapproval Requirements).

(b-1)

Notwithstanding Subsection (a) or (b), if a groundwater availability certification is required under Section 212.0101 (Additional Requirements: Use of Groundwater), the 30-day period described by those subsections begins on the date the applicant submits the groundwater availability certification to the municipal authority responsible for approving plats or the governing body of the municipality, as applicable.

(b-2)

Notwithstanding Subsection (a) or (b), the parties shall extend the 30-day period described by those subsections for one or more periods, each not to exceed 30 days if:

(1)

both:

(A)

the applicant requests the extension in writing to the municipal authority responsible for approving plats or the governing body of the municipality, as applicable; and

(B)

the municipal authority or governing body, as applicable, approves the extension request; or

(2)

Chapter 2007 (Governmental Action Affecting Private Property Rights), Government Code, requires the municipality to perform a takings impact assessment in connection with the plan or plat.

(c)

If a plat is approved, the municipal authority giving the approval shall endorse the plat with a certificate indicating the approval. The certificate must be signed by:

(1)

the authority’s presiding officer and attested by the authority’s secretary; or

(2)

a majority of the members of the authority.

(d)

If the municipal authority responsible for approving plats fails to approve, approve with conditions, or disapprove a plat within the prescribed period, the authority on the applicant’s request shall issue a certificate stating the date the plat was filed and that the authority failed to act on the plat within the period. The certificate is effective in place of the endorsement required by Subsection (c).

(e)

The municipal authority responsible for approving plats shall maintain a record of each application made to the authority and the authority’s action taken on it. On request of an owner of an affected tract, the authority shall certify the reasons for the action taken on an application.
Acts 1987, 70th Leg., ch. 149, Sec. 1, eff. Sept. 1, 1987.
Amended by:
Acts 2019, 86th Leg., R.S., Ch. 951 (H.B. 3167), Sec. 3, eff. September 1, 2019.
Acts 2019, 86th Leg., R.S., Ch. 951 (H.B. 3167), Sec. 4, eff. September 1, 2019.
Acts 2023, 88th Leg., R.S., Ch. 1125 (H.B. 3699), Sec. 8, eff. September 1, 2023.

Source: Section 212.009 — Approval Procedure: Initial Approval, https://statutes.­capitol.­texas.­gov/Docs/LG/htm/LG.­212.­htm#212.­009 (accessed Jun. 5, 2024).

212.001
Definitions
212.002
Rules
212.003
Extension of Rules to Extraterritorial Jurisdiction
212.004
Plat Required
212.005
Approval by Municipality Required
212.006
Authority Responsible for Approval Generally
212.007
Authority Responsible for Approval: Tract in Extraterritorial Jurisdiction of More than One Municipality
212.008
Application for Approval
212.009
Approval Procedure: Initial Approval
212.010
Standards for Approval
212.011
Effect of Approval on Dedication
212.012
Connection of Utilities
212.013
Vacating Plat
212.014
Replatting Without Vacating Preceding Plat
212.0015
Construction of Subchapter
212.015
Additional Requirements for Certain Replats
212.016
Amending Plat
212.017
Conflict of Interest
212.018
Enforcement in General
212.0021
Subdivision Requirements
212.0025
Chapter-wide Provision Relating to Regulation of Plats and Subdivisions in Extraterritorial Jurisdiction
212.041
Municipality Covered by Subchapter
212.042
Application of Subchapter a
212.043
Definitions
212.044
Plans, Rules, and Ordinances
212.0045
Exception to Plat Requirement: Municipal Determination
212.045
Development Plat Required
212.0046
Exception to Plat Requirement: Certain Property Abutting Aircraft Runway
212.046
Restriction on Issuance of Building and Other Permits by Municipality, County, or Official of Other Governmental Entity
212.047
Approval of Development Plat
212.048
Effect of Approval on Dedication
212.049
Building Permits in Extraterritorial Jurisdiction
212.050
Enforcement
212.0065
Delegation of Approval Responsibility
212.071
Developer Participation Contract
212.072
Duties of Parties Under Contract
212.073
Performance Bond
212.074
Additional Safeguards
212.0081
Required Application Materials
212.0085
Approval Procedure: Applicability
212.0091
Approval Procedure: Conditional Approval or Disapproval Requirements
212.0093
Approval Procedure: Applicant Response to Conditional Approval or Disapproval
212.0095
Approval Procedure: Approval or Disapproval of Response
212.0096
Approval Procedure: Alternative Approval Process
212.0097
Approval Procedure: Waiver Prohibited
212.0099
Judicial Review of Disapproval
212.0101
Additional Requirements: Use of Groundwater
212.101
Application of Subchapter to Certain Home-rule Municipality
212.102
Definitions
212.103
Traffic or Traffic Operations
212.104
Provision Not Enforceable
212.105
Subchapter Controls
212.0105
Water and Sewer Requirements in Certain Counties
212.0106
Bond Requirements and Other Financial Guarantees in Certain Counties
212.0115
Certification Regarding Compliance with Plat Requirements
212.131
Definitions
212.132
Applicability
212.133
Procedure for Adopting Moratorium
212.134
Notice and Public Hearing Requirements
212.135
Justification for Moratorium: Shortage of Essential Public Facilities
212.136
Expiration of Moratorium
212.137
Waiver Procedures Required
212.138
Effect on Other Law
212.139
Limitation on Moratorium
212.0145
Replatting Without Vacating Preceding Plat: Certain Subdivisions
212.0146
Replatting Without Vacating Preceding Plat: Certain Municipalities
212.151
Municipality Covered by Subchapter
212.152
Definition
212.153
Suit to Enforce Restrictions
212.154
Limitation on Enforcement
212.0155
Additional Requirements for Certain Replats Affecting a Subdivision Golf Course
212.155
Notice to Purchasers
212.156
Enforcement by Ordinance
212.157
Governmental Function
212.158
Effect on Other Law
212.171
Applicability
212.172
Development Agreement
212.173
Certain Coastal Areas
212.174
Municipal Utilities
212.0175
Enforcement in Certain Counties
212.201
Definitions
212.202
Applicability
212.203
Construction
212.204
Exclusive Authority
212.205
Parkland Dedication, Fee, or Combination
212.206
Request for Parkland Dedication Determination
212.207
Parkland Dedication Authority
212.208
Limitation on Parkland Dedication Amount
212.209
Initial Requirements for Determining Fees
212.210
General Requirements for Calculation of Fees
212.211
Requirements Calculation of Fees for Municipalities with Low Fees
212.212
Collection of Fees
212.213
Appeal
212.901
Developer Required to Provide Surety
212.902
School District and Open-enrollment Charter School Land Development Standards
212.903
Construction and Renovation Work on County-owned Buildings or Facilities in Certain Counties
212.904
Apportionment of Municipal Infrastructure Costs
212.905
Regulation of Tree Removal
212.906
Certain Value-based Fees and Disclosure of Certain Information Prohibited
212.1351
Justification for Moratorium: Significant Need for Public Facilities
212.1352
Justification for Commercial Moratorium in Certain Circumstances
212.1361
Notice for Extension Required
212.1362
Expiration of Moratorium on Commercial Property in Certain Circumstances
212.1535
Foreclosure by Property Owners’ Association

Accessed:
Jun. 5, 2024

§ 212.009’s source at texas​.gov