Tex.
Gov't Code Section 2269.256
Review of Bids or Proposals
(a)
The construction manager-at-risk shall review all trade contractor or subcontractor bids or proposals in a manner that does not disclose the contents of the bid or proposal during the selection process to a person not employed by the construction manager-at-risk, architect, engineer, or governmental entity. All bids or proposals shall be made available to the governmental entity on request and to the public after the later of the award of the contract or the seventh day after the date of final selection of bids or proposals.(b)
If the construction manager-at-risk reviews, evaluates, and recommends to the governmental entity a bid or proposal from a trade contractor or subcontractor but the governmental entity requires another bid or proposal to be accepted, the governmental entity shall compensate the construction manager-at-risk by a change in price, time, or guaranteed maximum cost for any additional cost and risk that the construction manager-at-risk incurs because of the governmental entity’s requirement that another bid or proposal be accepted.
Source:
Section 2269.256 — Review of Bids or Proposals, https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2269.htm#2269.256
(accessed Jun. 5, 2024).