Tex. Gov't Code Section 2253.045
Notice of Claim for Unpaid Labor or Material Under Written Unit Price Agreement


The notice for a claim for public work labor performed or public work material delivered by a payment bond beneficiary who is a subcontractor or materialman to the prime contractor or to a subcontractor and who has a written unit price agreement that is wholly or partially completed is sufficient if the beneficiary attaches to the sworn statement of account:

(1)

a list of units and unit prices set by the contract; and

(2)

a statement of those completed and partially completed units.
Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1, 1993.

Source: Section 2253.045 — Notice of Claim for Unpaid Labor or Material Under Written Unit Price Agreement, https://statutes.­capitol.­texas.­gov/Docs/GV/htm/GV.­2253.­htm#2253.­045 (accessed Apr. 13, 2024).

Accessed:
Apr. 13, 2024

§ 2253.045’s source at texas​.gov