By an order adopted and entered in the minutes of the commissioners court, and after a notice is published in English and Spanish in a newspaper of general circulation in the county, the commissioners court shall for each subdivision:

(1)

require a right-of-way on a street or road that functions as a main artery in a subdivision, of a width of not less than 50 feet or more than 100 feet;

(2)

require a right-of-way on any other street or road in a subdivision of not less than 40 feet or more than 70 feet;

(3)

require that the shoulder-to-shoulder width on collectors or main arteries within the right-of-way be not less than 32 feet or more than 56 feet, and that the shoulder-to-shoulder width on any other street or road be not less than 25 feet or more than 35 feet;

(4)

adopt, based on the amount and kind of travel over each street or road in a subdivision, reasonable specifications relating to the construction of each street or road;

(5)

adopt reasonable specifications to provide adequate drainage for each street or road in a subdivision in accordance with standard engineering practices;

(6)

require that each purchase contract made between a subdivider and a purchaser of land in the subdivision contain a statement describing how and when water, sewer, electricity, and gas services will be made available to the subdivision; and

(7)

require that the subdivider of the tract execute a bond in the manner provided by Section 232.027 (Bond Requirements).
Added by Acts 1995, 74th Leg., ch. 979, Sec. 4, eff. June 16 1995.

Source: Section 232.025 — Subdivision Requirements, https://statutes.­capitol.­texas.­gov/Docs/LG/htm/LG.­232.­htm#232.­025 (accessed Jun. 5, 2024).

232.001
Plat Required
232.002
Approval by County Required
232.003
Subdivision Requirements
232.004
Bond Requirements
232.005
Enforcement in General
232.006
Exceptions for Populous Counties or Contiguous Counties
232.007
Manufactured Home Rental Communities
232.008
Cancellation of Subdivision
232.009
Revision of Plat
232.010
Exception to Plat Requirement: County Determination
232.011
Amending Plat
232.0012
Construction of Subchapter
232.0013
Chapter-wide Provision Relating to Regulation of Plats and Subdivisions in Extraterritorial Jurisdiction
232.0015
Exceptions to Plat Requirement
232.0021
Plat Application Fee
232.021
Definitions
232.0022
Delegation of Approval Responsibility
232.022
Applicability
232.0023
Approval Procedure: Applicability
232.023
Plat Required
232.024
Approval by County Required
232.0025
Approval Procedure: Timely Approval of Plats
232.025
Subdivision Requirements
232.0026
Approval Procedure: Conditional Approval or Disapproval Requirements
232.026
Water and Sewer Service Extension
232.0027
Approval Procedure: Applicant Response to Conditional Approval or Disapproval
232.027
Bond Requirements
232.0028
Approval Procedure: Approval or Disapproval of Response
232.028
Certification Regarding Compliance with Plat Requirements
232.0029
Judicial Review of Disapproval
232.030
Subdivision Regulation
232.0031
Standard for Roads in Subdivision
232.031
Requirements Prior to Sale or Lease
232.0032
Additional Requirements: Use of Groundwater
232.032
Services Provided by Subdivider
232.0033
Additional Requirements: Future Transportation Corridors
232.033
Advertising Standards and Other Requirements Before Sale
232.0034
Additional Requirements: Access by Emergency Vehicles
232.034
Conflict of Interest
232.035
Civil Penalties
232.036
Criminal Penalties
232.037
Enforcement
232.038
Suit by Private Person in Economically Distressed Area
232.039
Cancellation of Subdivision
232.040
Replatting
232.041
Revision of Plat
232.042
Variances from Replatting Requirements
232.043
Variances from Platting Requirements
232.044
Amending Plat
232.0045
Financial Guarantee in Lieu of Bond
232.0048
Conflict of Interest
232.071
Applicability
232.072
Plat Required
232.073
Approval by County Required
232.074
Bond Requirements
232.075
Water and Sewer Service Extension
232.076
Certification Regarding Compliance with Plat Requirements
232.077
Connection of Utilities in Certain Counties
232.078
Conflict of Interest
232.079
Civil Penalties
232.080
Enforcement
232.081
Amending Plat
232.0083
Cancellation of Certain Subdivision Plats if Existing Plat Obsolete
232.0085
Cancellation of Certain Subdivisions if Land Remains Undeveloped
232.091
Applicability
232.092
Establishment and Abolition of Planning Commission
232.093
Appointment of Members of Planning Commission
232.094
Financial Disclosure
232.0095
Alternative Procedures for Plat Revision
232.095
Officers, Quorum, and Meetings
232.096
Timely Approval of Plats
232.097
Reasons for Disapproval of Plat Required
232.101
Rules
232.102
Major Thoroughfare Plan
232.103
Lot Frontages
232.104
Set-backs
232.105
Developer Participation Contracts
232.106
Connection of Utilities
232.107
Provisions Cumulative
232.108
Plat Requirements
232.109
Fire Suppression System
232.110
Apportionment of County Infrastructure Costs
232.151
Applicability
232.152
Administrative Determination
232.153
Public Hearing
232.154
Notice of Hearing
232.155
Judicial Review
232.156
Civil Action for Receivership
232.157
Authority and Duty of Receiver
232.158
Sale of Property
232.00285
Development Plan Review
232.0305
County Inspector
232.0315
Notice of Water and Wastewater Requirements by Political Subdivisions
232.0775
County Inspector
232.901
Certain Value-based Fees and Disclosure of Certain Information Prohibited

Accessed:
Jun. 5, 2024

§ 232.025’s source at texas​.gov